Assign a code to unplanned work

Hours logged as "Need a code" wait on the Verify screen until the estimator or a superintendent picks the line item.

When crew log work that isn’t on the estimate, they mark it Need a code and describe it. The estimator gets an email about it.

Estimators and Superintendents can assign codes. Which one does it depends on how your company works.

  1. Tap Verify

    Entries waiting for a code are marked Need a code and show the crew’s description.
  2. Pick the line item

    Under Pick a line item…, choose the right one and tap Assign code.
  3. Approve it

    Once it has a code, a foreman or superintendent taps Approve.

Until they get a code, those hours don’t count in any line item’s totals. The scoreboard and Dashboard show them in red, and downloads warn about them.

If the work isn’t on the estimate at all, the estimator adds a line item for it first.