For Estimators. Lock the baseline when the estimate is ready, ideally before crews start logging.
Tap Lock baseline
It’s under Baseline on the project’s estimate.Read the summary
Today’s estimate is saved as the baseline and never overwritten. Every later change needs a reason. Spreadsheet upload is turned off for this project.Tap Lock baseline again
The estimate now shows when it was locked and by whom.
Changing the estimate after locking
Section titled “Changing the estimate after locking”Edit, add or remove line items as usual. Each change asks for a Reason, like “Owner added a deck”, and an optional Change order #. Removed items are kept in history.
Seeing what changed
Section titled “Seeing what changed”Tap Revisions on the estimate. It shows Baseline hours against Revised hours, the Difference, and a History of every change.
[SCREENSHOT: Revisions page]