Skip to content
H5 TOOLS HELP
Start free trial

Production Tracking Estimator & Admin

Lock the baseline and track revisions

Keep the original estimate for good, and record every later change with a reason.

For Estimators. Lock the baseline when the estimate is ready, ideally before crews start logging.

  1. Tap Lock baseline

    It’s under Baseline on the project’s estimate.
  2. Read the summary

    Today’s estimate is saved as the baseline and never overwritten. Every later change needs a reason. Spreadsheet upload is turned off for this project.
  3. Tap Lock baseline again

    The estimate now shows when it was locked and by whom.

Edit, add or remove line items as usual. Each change asks for a Reason, like “Owner added a deck”, and an optional Change order #. Removed items are kept in history.

Tap Revisions on the estimate. It shows Baseline hours against Revised hours, the Difference, and a History of every change.

[SCREENSHOT: Revisions page]